Thursday, April 26, 2012
New siding and new milgard windows arrive
shear wall and straps
Wednesday, April 25, 2012
Sheeting on 1st floor. Shearwall and hold downs signed off by city.
insulation on 1st floor
stripping west wall and framing
seizmic upgrades
Monday, April 23, 2012
Roofing completed
seizmic upgrades
Wednesday, April 18, 2012
New roof and tar papered. Sheer wall inspection passed
plumbing inspected and passed